A project at month 5 had an actual cost of $34,000, a planned value of $ 42,000,

Question:

A project at month 5 had an actual cost of $34,000, a planned value of $ 42,000, and an earned value of $ 39,000. Find the cost and schedule variances.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations And Supply Chain Management For MBAs

ISBN: 9781119355328

6th Edition

Authors: Jack R. Meredith, Scott M. Shafer

Question Posted: