As in the situation shown in Figure 2.16, a project at month 2 exhibited an actual cost

Question:

As in the situation shown in Figure 2.16, a project at month 2 exhibited an actual cost of $ 78,000, a planned value of $84,000, and a value completed of $81,000. Find the cost and schedule variances. Estimate the time variance.