If unit 1 required 200 hours to produce and the labor records for an Air Force contract
Question:
If unit 1 required 200 hours to produce and the labor records for an Air Force contract of 50 units indicate an average labor content of 63.1 hours per unit, what was the learning rate? What total additional number of labor hours would be required for another Air Force contract of 50 units? What would be the average labor content of this second contract? Of both contracts combined? If labor costs the vendor $10 per hour on this Air Force contract and the price to the Air Force is fixed at $550 each, what can you say about the profitability of the first and second contracts and hence the bidding process in general?