4. Mr. Baker, the scheduler at Idaho Manufacturing Company, has developed the following tentative master schedule for
Question:
4. Mr. Baker, the scheduler at Idaho Manufacturing Company, has developed the following tentative master schedule for the next 6 months and wants to evaluate it.
The following bill of labor gives the hours required in each of the company’s five key work centers to make one unit of the company’s products.
Develop the capacity requirements for each of the next 6 months—that is, the load profile—for department 2.