A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure 14.14.

Question:

A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure 14.14. From the information shown, generate:

a) An indented bill of material for product A (see Figure 5.9 in Chapter 5 as an example of a BOM).

b) Net requirements for each part to produce 10 As in week 8 using lot-for-lot. lop5