Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers.

Question:

Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The following table highlights the time taken in hours for (1) cutting and sewing and (2) delivery of each of the suits. Which schedule finishes sooner: L 0 1 

first come, first served (123) or a schedule using Johnson’s rule?

Times Taken for Different Activities (hours)

SUIT CUT AND SEW DELIVER 1 4 2 2 7 7 3 6 5