The following jobs are waiting to be processed at Jeremy LaMontagnes machine center. Today is day 250.

Question:

The following jobs are waiting to be processed at Jeremy LaMontagne’s machine center. Today is day 250. L 0 1 

JOB DATE JOB RECEIVED PRODUCTION DAYS NEEDED DATE JOB DUE 1 215 30 260 2 220 20 290 3 225 40 300 4 240 50 320 5 250 20 340 Using the critical ratio scheduling rule, in what sequence would the jobs be processed?