A business is launching a new product. The launch will require a number of related activities as

Question:

A business is launching a new product. The launch will require a number of related activities as follows - hire a sales manager (5 weeks), require the sales manager to recruit sales people (4 weeks), train the sales people (7 weeks), select an advertising agency (2 weeks), plan an advertising campaign with the agency (4 weeks), conduct the advertising campaign (10 weeks), design the packaging of the product (4 weeks), set up packing operation (12 weeks), pack enough products for the launch stock (8 weeks), order the launch quantity of products from the manufacturer (13 weeks), select distributors for the product (9 weeks), take initial orders from the distributors (3 weeks), despatch the initial orders to the distributors (2 weeks).
(a) What is the earliest time that the new product can be introduced to the market?
(b) If the company hires trained salesmen who do not need further training, could the product be introduced seven weeks earlier?
(c) How long could one delay selecting the advertising agency?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 9780273708476

5th Edition

Authors: Nigel Slack, Stuart Chambers, Robert Johnston

Question Posted: