A foreman has determined the expected processing times at a machine for a set of jobs and now wants to sequence them. Given the information shown below, do the following:
a. Determine the processing sequence using (1) MST,(2) SPT, (3) EDD, and (4)CR- For each sequence, calculate the average days late, the average flow time, and the average WIP.
b. Which rule is best?