A job was timed for 60 cycles and had an average of 1.2 minutes per piece. The

Question:

A job was timed for 60 cycles and had an average of 1.2 minutes per piece. The performance rating was 95 percent, and workday allowances are 10 percent.
Determine each of the following:
a. Observed time.
b. Normal time.
c. Standard time.