A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the

Question:

A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project? 

a. 3 days, because this is the minimum time 

b. 7 days, because this is the maximum time 

c. 20 days, because this is the sum of the times 

d. It is not possible to determine the total completion time from the given information.