A shop works a 400-minute day. The manager of tire shop wants an output rate of 200

Question:

A shop works a 400-minute day. The manager of tire shop wants an output rate of 200 units per day for the assembly line that has the tasks shown in the following table. Do the following:
a. Construct the precedence network and calculate the cycle time.
b. Assign tasks according to “Assign the task with the most followers” rule. In the case of a tie, use “Assign tire task with the longest time” heuristic rule.
c. Calculate the balance delay.

image text in transcribed