Consider the construction of a research building for Eli Lilly & Co., a pharmaceutical company, a few
Question:
Consider the construction of a research building for Eli Lilly & Co., a pharmaceutical company, a few years ago. This 550,000 ft2, 4-story (in 3 wings), $135 million building was planned to be completed in five years. It required special ventilation for 162 labs, purified water, and special drainage. Consider the following list of major activities/work packages (as seen by Eli Lilly), their expected duration, and their relationship to other activities/work packages for the Eli Lilly building.
b. Determine the ES, EF, LF, and LS times.
c. What is the project duration?
d. What are the critical activities?