Use the following activities and their three duration estimates (in days) to do the following: a. Determine

Question:

Use the following activities and their three duration estimates (in days) to do the following:
a. Determine the expected duration of the project.
b. Calculate the probability' that the project will take at least 18 days.

image text in transcribed
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0071091428

4th Canadian edition

Authors: William J Stevenson, Mehran Hojati

Question Posted: