Consider the data given in the following table and answer the questions that follow. a. What is
Question:
Consider the data given in the following table and answer the questions that follow.
a. What is the normal project time?
b. Identify the critical path?
c. What is the normal cost of the project?
d. If the project time is to be reduced by one day, which activity should be crashed first? What is the cost of crashing per day of activity E?