Eighty units of product E are needed at the beginning of week 6. Three cases (30 units
Question:
Eighty units of product E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J on hand now. Manufacturing lead times are two weeks each for E and B, and purchase lead time is one week for J.
b. Suppose that now is week 4 and the quantity of E needed in week 6 has changed from 80 to 70. The planned order releases through week 3 and scheduled receipts have all been executed as in part α. How many more (relative to part a) Bs and Js will be on Land in week 6?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management
ISBN: 978-0071091428
4th Canadian edition
Authors: William J Stevenson, Mehran Hojati
Question Posted: