Path A-B-E has a 55% probability of being completed within 3 weeks. Path C-D-F has a 90%

Question:

Path A-B-E has a 55% probability of being completed within 3 weeks. Path C-D-F has a 90% probability of being completed within 3 weeks. If these are the only two paths in a project network, what is the probability the project will be completed in 3 weeks?