Refer to the data in problem 6. If backorders are allowed, determine the total cost of a
Question:
Data from problem 6
Given the following forecast and cost information, determine the total cost of a plan that uses regular time production output of 600 units per month, overtime is used when needed up to a maximum of 60 units per month, and subcontracting is used if additional units are needed to meet the forecast:
Regular time cost = $40 per unit
Overtime cost = $60 per unit
Subcontracting cost = $80 per unit
Holding cost = $10 per unit per month