Table 7.8 contains data for the installation of imported generators from Germany in your office premises in
Question:
Table 7.8 contains data for the installation of imported generators from Germany in your office premises in Nigeria. The indirect costs are €200 per week, and a penalty cost of €900 per week will be incurred by your company for every week the project is delayed beyond week 50 days.
a. What is the shortest time duration for this project regardless of cost?
b. What is the total cost associated with completing the project using "normal" times?
c. What is the total time of the minimum-cost schedule?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management Processes And Supply Chains
ISBN: 9781292409863
13th Global Edition
Authors: Lee Krajewski, Naresh Malhotra, Larry Ritzman
Question Posted: