Table contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your
Question:
a. What is the shortest time duration for this project regardless of cost?
b. What is the minimum total cost associated with completing the project in 9 weeks?
c. What is the total time of the minimum-costschedule?