The average demand is equal to 10 units per day, the order lead time is 7 days,

Question:

The average demand is equal to 10 units per day, the order lead time is 7 days, and the standard deviation of the lead time demand is 4 units. If a 95 percent service level is desired, what is the reorder point?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: