The following table shows orders to be processed at a machine as of 8 a.m., Monday. Jobs
Question:
The following table shows orders to be processed at a machine as of 8 a.m., Monday. Jobs are listed in the order of arrival.
a. Determine the processing sequence using each of these priority rules: (1) CR, (2) MST, (3) SPT, (4) EDD.
b. Determine tire performance of each rule using (1) average flow time, (2) average days late.
c. Is one rule superior to the others?