The following table shows the data collected about a project. For the above project: (a) Draw an

Question:

The following table shows the data collected about a project.

image text in transcribed

For the above project:

(a) Draw an activity-on-arrow diagram showing the duration of each activity, the earliest start and latest finish times

(b) Draw an activity-on-node diagram

(c) Determine the completion time and the project cost

(d) Identify the critical activities

(e) Calculate the total and free floats.

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management In Context

ISBN: 978-1138455535,978-0750681988

2nd Edition

Authors: Frank Rowbotham , Masoud Azhashemi ,Les Galloway

Question Posted: