The following table shows the data collected about a project. For the above project: (a) Draw an
Question:
The following table shows the data collected about a project.
For the above project:
(a) Draw an activity-on-arrow diagram showing the duration of each activity, the earliest start and latest finish times
(b) Draw an activity-on-node diagram
(c) Determine the completion time and the project cost
(d) Identify the critical activities
(e) Calculate the total and free floats.
Step by Step Answer:
Related Book For
Operations Management In Context
ISBN: 978-1138455535,978-0750681988
2nd Edition
Authors: Frank Rowbotham , Masoud Azhashemi ,Les Galloway
Question Posted: