The table below contains information about five jobs waiting to be processed at stamping machine 307 in

Question:

The table below contains information about five jobs waiting to be processed at stamping machine 307 in the MetalBright Job Shop.

image text in transcribed

a. Which of these three rules provides the best sequence in terms of average flow- time: EDD, critical ratio, or SPT?

b. Which of these three rules provides the best sequence in terms of average tardi- ness: EDD, critical ratio, or SPT?

c. In each of the three sequences, when will job C be finished?