The welding department supplies parts to the final assembly line. Management decides to implement a kanban system

Question:

The welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data: 

a. The daily demand is 2000 units. 

b. The production lead time is 4 days (this includes processing time, transport time, and waiting time). 

c. Management has decided to have 1 day of safety stock. 

d. One container fits 400 units. How many kanban containers will be needed to support this system?