The welding department supplies parts to the final assembly line. Management decides to implement a kanban system
Question:
The welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data:
a. The daily demand is 2000 units.
b. The production lead time is 4 days (this includes processing time, transport time, and waiting time).
c. Management has decided to have 1 day of safety stock.
d. One container fits 400 units. How many kanban containers will be needed to support this system?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management
ISBN: 9781260547610
2nd International Edition
Authors: Gerard Cachon, Christian Terwiesch
Question Posted: