Using AOA, diagram the network described below for Roni Zuckerman€™s construction project. Calculate its critical path. How long is the minimum duration of this network?

Time (weeks) Time Nodes (weeks) Activity Nodes 10 Activity J 3-4 1-2 N K 1-3 4-5 3-5 5 2-4 2-4 3 2-3