Question: Using AOA, diagram the network described below for Roni Zuckermans construction project. Calculate its critical path. How long is the minimum duration of this network?

Using AOA, diagram the network described below for Roni Zuckerman€™s construction project. Calculate its critical path. How long is the minimum duration of this network?

Time (weeks) Time Nodes (weeks) Activity Nodes 10 Activity J 3-4 1-2 N K 1-3 4-5 3-5 5 2-4 2-4 3 2-3

Time (weeks) Time Nodes (weeks) Activity Nodes 10 Activity J 3-4 1-2 N K 1-3 4-5 3-5 5 2-4 2-4 3 2-3

Step by Step Solution

3.35 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The paths through this network a... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

1496_60b7412250166_647483.pdf

180 KBs PDF File

Word file Icon

1496_60b7412250166_647483.docx

120 KBs Word File

Students Have Also Explored These Related Operations Management Questions!