You manage a project with 10 activities. Activities A 1 , A 3 , A 5 ,

Question:

You manage a project with 10 activities. Activities A1, A3, A5, and A9 form the critical path. Because you have a large budget for the project, you consider crashing activity A2, which has the potential to shorten the time of A2 by three days. What do you think about this opportunity? 

a. It is a good idea because it will reduce the project duration by three days. 

b. It is a bad idea because A2 is not on the critical path.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 9781260547610

2nd International Edition

Authors: Gerard Cachon, Christian Terwiesch

Question Posted: