Consider two projects that have the same activities and the same dependencies. In the first project, the

Question:

Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected outcomes. The actual times will vary. In the second project, the activity times are always as expected. Assuming the expected activity times are identical across the two projects, which project will be completed first? 

a. The first 

b. The second 

c. Cannot be determined

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 9781260547610

2nd International Edition

Authors: Gerard Cachon, Christian Terwiesch

Question Posted: