7 A project is considered completed when activities AF have all been completed. The duration and predecessors

Question:

7 A project is considered completed when activities A–F have all been completed. The duration and predecessors of each activity are given in Table 43. The LINDO output in Figure 69 can be used to determine the critical path for this project.

a Use the LINDO output to draw the project network.

Indicate the activity represented by each arc.

b Determine a critical path in the network. What is the earliest the project can be completed?

image text in transcribed

image text in transcribed

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: