In Example 16.1-2, suppose that the demand during lead time is uniform between 40 and 60 gallons.
Question:
In Example 16.1-2, suppose that the demand during lead time is uniform between 40 and 60 gallons. Compare the solution with that obtained in Example 16.1-2, and interpret the results. (Hint: In both problems, E5x6 is the same, but the variance in the present problem is smaller.)