In Problem 9-41, suppose that job 4 cannot be processed until job 3 has been completed. Also,

Question:

In Problem 9-41, suppose that job 4 cannot be processed until job 3 has been completed.

Also, machine settings for jobs 7 and 8 necessitate processing them one right after the other (i.e., job 7 immediately succeeds or precedes job 8). Jobco’s objective is to process all ten jobs with the smallest sum of due-time violations. Formulate the model mathematically, and determine the optimum solution.