25. You were in the middle of a two-year project to deploy new tedmology to field office.~...
Question:
25. You were in the middle of a two-year project to deploy new tedmology to field office.~ across the country. A hurricane ..:aused power out,1gcs just when thl' upgrade was near completion. V..'hen the power was restored, all the project reports .md historical data were lost, with no way of retrieving them.
'What should have been done to prevent this problem!
A. Purchase insurance.
B. Plan for a reserve fund.
C. Monitor the weather and have a contingency plan.
D. Schedule the installation outside of the hurncane se.1son.