A project consisting of eight activities satisfies the following precedence constraints: Time Immediate Activity (weeks) Predecessors A
Question:
A project consisting of eight activities satisfies the following precedence constraints:
Time Immediate Activity (weeks) Predecessors A 3 B 5 A C 1 A D 4 B, C E 3 B F 3 E, D G 2 F H 4 E, D
a. Construct a network for this project. (You should need only one pseudo activity.)
b. Compute the earliest and the latest starting and finishing times for each activity and identify the critical path.
c. Draw a Gantt chart of the schedule for this project based on earliest starting times.