For the project network pictured in Figure 108, a. List the immediate predecessors of each activity. b.

Question:

For the project network pictured in Figure 10–8,

a. List the immediate predecessors of each activity.

b. Try to determine the critical path by enumerating all paths from node 1 to node 10.

c. Compute the earliest starting and finishing times for all activities and identify the critical activities.