Answer the following questions for Example 10.4. a. What event is represented by node 6 in Figure
Question:
Answer the following questions for Example 10.4.
a. What event is represented by node 6 in Figure 10–5?
b. What group of activities will have to be completed by week 16 in order to guarantee that the project will not be delayed?
c. Suppose that module 4 is coded by a subcontractor who delivers the module after 7 weeks. How much will it delay the project if the subcontractor does not start until week 11?