Suppose that the normal and the expedited costs and times are as given in the following table.
Question:
Suppose that the normal and the expedited costs and times are as given in the following table.
Normal Expedited Normal Expedited Activity Time Time Cost Cost A 32 26 $ 200 $ 500 B 21 20 300 375 C 30 30 200 200 D 45 40 500 800 E 26 20 700 1,360 F 28 24 1,000 1,160 G 20 18 400 550 If indirect costs amount to $100 per day, determine the optimal time to complete the project and the optimal project completion cost.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Production And Operations Analysis
ISBN: 9781478623069
7th Edition
Authors: Steven Nahmias, Tava Lennon Olsen
Question Posted: