13.15 The production planning period for mobile boards at Sime Factory, Egypt, is 4 months. Cost data
Question:
• • 13.15 The production planning period for mobile boards at Sime Factory, Egypt, is 4 months. Cost data are as follows:
For each of the next 4 months, capacity and demand data for boards are as follows:
Develop a production plan that minimizes costs using the transportation method. Assume beginning inventory at 200 boards and backorders are permitted.