A time study engineer has studied the time taken to machine crank shafts. He has taken 40
Question:
A time study engineer has studied the time taken to machine crank shafts. He has taken 40 observations and these are summarized in the form of frequency distribution as shown below:
Time (Minutes) Frequency 20 15 21 10 22 10 23 5 The performance rating of the operator machining the crank shaft is 110 per cent. Find the standard time for machining the crank shaft by assuming allowance of 15 per cent.