In the McNaughton's algorithm to minimize the makespan in the single machine scheduling problem with parallel processors,

Question:

In the McNaughton's algorithm to minimize the makespan in the single machine scheduling problem with parallel processors, of the jobs is assumed.

(a) Pre-emption

(b) Non-pre-emption

(c) Dependency

(d) None of the above.