In , the peak manpower requirement is minimised without extending the project completion time. (a) Resource allocation

Question:

In , the peak manpower requirement is minimised without extending the project completion time.

(a) Resource allocation

(b) PERT

(c) Network crashing

(d) Resource levelling.