Question: 10.11 Given the following information, answer the questions about this project: Activity Expected Duration Predecessors A 4 days B 9 days A C 11

10.11 Given the following information, answer the questions about this project:

Activity Expected Duration Predecessors A 4 days —

B 9 days A C 11 days A D 5 days B E 3 days B F 7 days C G 3 days D, F H 2 days E, G I 1 day H