Question: 10.10 Develop a Gantt chart with the following information. What is the expected duration of the project? What is the critical path? Activity Expected Duration
10.10 Develop a Gantt chart with the following information.
What is the expected duration of the project? What is the critical path?
Activity Expected Duration Predecessors A 12 None B 8 None C 5 None D 10 A and B E 10 C and D F 5 A and B