Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Tutorial 04 Questions 1. Construct a network activity diagram based on the following information: Activity Preceding Activities A E B A C A D A

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed
Tutorial 04 Questions 1. Construct a network activity diagram based on the following information: Activity Preceding Activities A E B A C A D A E B F C.D G E.F H F I G.H J I 2. You have a partial network for your project, and you are about to conduct a forward pass through it. Explain why the early start (ES) for activity G is 23 days, not 19 days. Remember, activity G is a merge activity. 16 E 23 7 G 4 14 F 19 5Referring to the figure above in question 2, suppose that Activity G was the last activity in the network and you were about the start a backward pass. a. What is the project's duration? (Hint: complete the forward pass) b. What are the late finish (LF) and late start (LS) values for Activities E, F, and G? c. Which activity has slack time? How many days? Referring to the figure shown below, suppose that Activity O was the last activity in the network and you were about to start a backward pass. a. What is the project's duration? (Hint: complete the forward pass) b. What are the late finish (LF) and late start (LS) values for activities L, M, N, and O? c. Which activities have slack time? How many days? and you were about to start a backward pass. a. What is the project's duration? (Hint: complete the forward pass) b. What are the late finish (LF) and late start (LS) values for activities L, M, N, and O? c. Which activities have slack time? How many days? The University of the South Pacific 1S333 Tutorial 03 Questions and Possible Solutions Page 1 0of 3 1S333: Project Management Tutorial 04 Questions and Answers 14 N 16 Y our university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. 2 Construct a network activity diagram based on the following information: Activity Description Predecessors Duration (Days) A Site selection None 4 B Buy concessions A 4 C Rent facilities A 2 D Build stands A 5 E Generator & wiring installation C 2 F Security B 4 G Lighting installation E 2 H Sound system installation E,F 2 I Stage construction D 3 J Tear down G,H, 1 4 a. Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project? b. Identify all paths through the network. Which is the critical path? c. Which activities have slack time? d. Identify all burst activities and merge activities. 6. Explain the concept of a \"dummy variable.\" Why is this concept employed in AOA notation? Why is there no need to use dummy variables in an AON network? 7. Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors a. Create the Activity Network Diagram using the (AoN) technique. (Question repeated from Tutorial 3, remove any redundant member) 8. Develop the AOA diagram based on the following information. The University of the South Pacific 1S333 Tutorial 03 Questions and Possible Solutions Page 2 of 3 15333: Project Management Tutorial 04 Questions and Answers Activity Predecessor 9. Develop a Gantt chart with the following information. What is the expected duration of the project? What is the critical path? Activity Expected Duration Predecessors A 12 None B 8 None C 5 None D 10 A and B E 10 C and D F 5 A and B10. Consider a project with the following information. Construct the project activity network using AOA methodology and label each node and arrow appropriately. Identify all dummy activities required to complete the network. Activity Duration Predecessors A 3 = B 3 A C 7 A D 3 B.C E 5 B F 4 D G 2 C H 3 E.E.G Activity Duration ES EF LS LF Slack A 3 0 3 0 3 B 5 3 8 5 10 2 C 3 10 3 10 D 3 10 13 10 13 E 5 8 13 12 17 4 F - 13 17 13 17 _ G 2 10 12 15 17 5 H 5 17 22 17 22

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Retailing Management

Authors: Michael Levy

11th Edition

1264157444, 9781264157440

More Books

Students also viewed these General Management questions

Question

=+Describe the components of this time series.

Answered: 1 week ago

Question

What products or services does your key public commonly use?

Answered: 1 week ago

Question

What position do you seek?

Answered: 1 week ago