Question: 7 Because of resource constraints, Activity I cannot begin until January 29. I is loaded five days late. Total delay for Activity I is 2

7 Because of resource constraints, Activity I cannot begin until January 29. I is loaded five days late.

Total delay for Activity I is 2 days (new finish date = February 2).