A project (fixed-rate contract) was scheduled to commence on a particular date as per the letter of

Question:

A project (fixed-rate contract) was scheduled to commence on a particular date as per the letter of intent issued by the owner. Owing to certain reasons attributable to the owner, the handing-over of the site got delayed. Ultimately, it was handed over to the contractor after a delay of six months.

As the contractor, what action would you like to take?