During heavy monsoon, the site of works got completely submerged in water, including plant and machinery, materials
Question:
During heavy monsoon, the site of works got completely submerged in water, including plant and machinery, materials and infrastructure. How will you attribute the delay in works due to the above? What actions would you take as a contractor to salvage the situation including the losses?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Construction Project Management Theory And Practices
ISBN: 9789332542013
2nd Edition
Authors: Kumar Neeraj Jha
Question Posted: