I n a building project, delays take place, and the contractor applies for extension of time by
Question:
I n a building project, delays take place, and the contractor applies for ‘extension of time’ by citing various reasons as attributable to the owner, before the expiry of the contractual completion date.
No action is taken on the above by the owner. Meanwhile, the owner levies liquidated damages on the contractor and recovers the same from the contractor’s bills. Is the owner correct in his action?
Comment.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Construction Project Management Theory And Practices
ISBN: 9789332542013
2nd Edition
Authors: Kumar Neeraj Jha
Question Posted: