I n a building project, delays take place, and the contractor applies for extension of time by

Question:

I n a building project, delays take place, and the contractor applies for ‘extension of time’ by citing various reasons as attributable to the owner, before the expiry of the contractual completion date.

No action is taken on the above by the owner. Meanwhile, the owner levies liquidated damages on the contractor and recovers the same from the contractor’s bills. Is the owner correct in his action?

Comment.