Activity A is worth ($400,) is 100% complete, should have been done on day 1, and actually

Question:

Activity A is worth \($400,\) is 100% complete, should have been done on day 1, and actually cost \($400.\) Activity B is worth \($150,\) is 90% complete, should have been done on day 2, and actually cost \($240\) so far. Activity C is worth \($400,\) is 75% complete and should have been done on day 3, and has cost \($350\) so far. The total budget is \($2,000.\) What is the planned value as of day 3?

a. \($950.00\)

b. \($950.00\)

c. \($990.00\) 

d. -\($990.00\)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: