Activity A is worth ($400,) is 100% complete, should have been done on day 1, and actually
Question:
Activity A is worth \($400,\) is 100% complete, should have been done on day 1, and actually cost \($400.\) Activity B is worth \($150,\) is 90% complete, should have been done on day 2, and actually cost \($240\) so far. Activity C is worth \($400,\) is 75% complete and should have been done on day 3, and has cost \($350\) so far. The total budget is \($2,000.\) What is the planned value as of day 3?
a. \($950.00\)
b. \($950.00\)
c. \($990.00\)
d. -\($990.00\)