Activity A is worth ($800,) is 100% complete, and actually cost ($800.) Activity B is worth ($300,)

Question:

Activity A is worth \($800,\) is 100% complete, and actually cost \($800.\) Activity B is worth \($300,\) is 90% complete, and actually cost \($480\) so far. Activity C is worth \($800,\) is 75% complete, and has cost \($700\) so far. The total budget is \($4,000.\) What is the cost performance index for the project?

a. 1.19

b. 0.88

c. 1.14

d. 0.84

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: