Activity A is worth ($800,) is 100% complete, and actually cost ($800.) Activity B is worth ($300,)
Question:
Activity A is worth \($800,\) is 100% complete, and actually cost \($800.\) Activity B is worth \($300,\) is 90% complete, and actually cost \($480\) so far. Activity C is worth \($800,\) is 75% complete, and has cost \($700\) so far. The total budget is \($4,000.\) What is the cost performance index for the project?
a. 1.19
b. 0.88
c. 1.14
d. 0.84
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: