Cost estimating should occur: a. Before the work breakdown structure is created and before the budget is
Question:
Cost estimating should occur:
a. Before the work breakdown structure is created and before the budget is developed
b. Before the work breakdown structure is created and after the budget is developed
c. After the work breakdown structure is created and before the budget is developed
d. After the work breakdown structure is developed and after the budget is developed